Muster replaces the daily cost Excel sheet. The site team enters the day, accounts check it twice, and an approved day downloads as the same Excel file as before. The project here holds demo data: try anything, nothing here is real work.

Before you start

RoleSign in asWhat they do
Sitesite@example.comFills in the day's sheet and submits it.
Accounts: 1st checkaccounts1@example.comChecks submitted sheets; approves or returns them.
Accounts: final approvalaccounts2@example.comGives the final approval; the sheet is then locked.
Adminadmin@example.comEverything, plus items, settings, import and users.

Passwords come from the person running the demo. To switch roles quickly, use a normal window for one role and a private window for another, or use “Sign out” at the top right.

The demo project holds one real day (21-11-2026, imported from the Excel file) and the days after it: 21-11-2026 and 22-11-2026 are final, 23-11-2026 waits for final approval, 24-11-2026 waits for the 1st check, and 25-11-2026 is a draft.

The demo in 9 steps

  1. 1

    Sign in and find your work any role

    Where: the sign-in page, then the dashboard

    Do: Sign in with a demo account. The dashboard's “Waiting for you” lists the sheets your role has to act on.

    Notice: Each role sees a different list. Status tags show where every day is in the chain.

  2. 2

    Enter today's sheet Site

    Where: Dashboard → “Open today's sheet” (or Today in the menu)

    Do: Every active item is already listed with yesterday's quantities. Change one or two numbers (press Enter to jump to the next box), then press Save & submit.

    Notice: Changed boxes turn yellow and the totals update as you type. Nothing has to be typed twice; Excel formulas are no longer needed.

  3. 3

    First check Accounts: 1st check

    Where: Dashboard → the sheet “Waiting for 1st check” (24-11-2026)

    Do: Read the warnings at the top (for example “14 hours is more than 12 in a day”). Either press Approve, or tick Query on the doubtful line, write what needs fixing and press Return to site.

    Notice: Only lines with warnings or notes are shown at first; untick the box to see all lines. The checker can also correct a number directly instead of sending it back.

  4. 4

    Fix a returned sheet Site

    Where: Dashboard → the sheet marked “Returned”

    Do: Read the red comment, correct the line marked Queried, then Save & submit again.

    Notice: The comment and the marked lines come straight from the checker, so there is no phone call or email chain.

  5. 5

    Final approval Accounts: final approval

    Where: Dashboard → the sheet “Waiting for final approval” (23-11-2026)

    Do: Press Approve as final.

    Notice: The sheet is now Final and locked. The same person cannot do two steps; only an admin can reopen a final sheet, with a reason.

  6. 6

    Approve clean days in one go Accounts

    Where: Dashboard → “Waiting for you”

    Do: Tick the sheets without warnings and press Approve selected. Optional: Settings → Approval → “Only sheets with warnings” makes clean days final after the 1st check.

    Notice: This is where the time saving is: clean days need one click instead of a line-by-line check by two people.

  7. 7

    Download Excel any role

    Where: a sheet → “Download Excel”; Reports → “Download month”

    Do: Download one day, then the whole month.

    Notice: The file has the same 17 columns as the old sheet, with RATE as a formula and AMOUNT = NOS × RATE. The month file has every day in one sheet.

  8. 8

    Supplier bills Accounts

    Where: Bills (in the menu)

    Do: Pick a supplier, type the bill number and amount, press Record bill. Open the supplier's name to see it item by item and day by day.

    Notice: The page shows whether the bill matches the daily sheets. The bill number goes into BILL NUMBER on every line of that supplier for the month.

  9. 9

    Admin tour Admin

    Where: Items, Rates, Users, Settings, Activity, Import

    Do: Change a rate “from” a date; add a user and copy their invite link; open Activity.

    Notice: Old days keep their old rate. Every change is recorded with who and when. Import builds the whole master list from one day's Excel sheet.

Tutorials

The daily sheet
  • Create: open a date with no sheet and press Create sheet. It lists every active item with the quantities of the previous sheet.
  • Enter: type the quantity (hours, days, litres, trips). Enter moves to the next box. Save keeps your work; Save & submit sends it for checking.
  • One-off line: “Add a one-off line” for something that happened only that day. Tick “Also add to the master list” if it will repeat.
  • Edit a line: click the item name to change its codes, unit, supplier or that day's rate.
  • Refresh from master list: on a draft, reloads items, rates and codes after you changed them; quantities are kept.
  • History: at the bottom of every sheet: who created, changed, submitted, checked and approved it.
Approval chain and who can change what
StatusWho actsWho can change lines
DraftSite: Save & submitSite, admin
Waiting for 1st checkAccounts 1: approve or returnAccounts 1, admin
Waiting for final approvalAccounts 2: approve or returnAccounts 2, admin
FinalAdmin: reopen (with a reason)Nobody

“Return to site” always needs a comment and can mark lines with “Query”. The same person cannot do two steps of one sheet.

Warnings and notes

Warnings (look at these): more hours in a day than the project limit (12); rate changed since the previous day; much higher than usual (more than twice the usual quantity); fuel booked on a day its machine shows 0; fuel booked to a different section than its machine (when new); a quantity with rate 0.

Notes (good to know): quantity changed since the previous day; new item; one-off line; no supplier (when new); items that were on the previous day but not on this one.

A monthly rate is not flagged just because a month has 30 or 31 days.

Rates
  • Each item has a rate: an amount, VAT % and how it is divided: per unit, monthly ÷ real days in the month, monthly ÷ days ÷ hours per day, or ÷ a fixed number.
  • Rates have dates. “New rate from a date” keeps every earlier day as it was.
  • All fuel lines share one Diesel rate, so a new fuel price is entered once.
  • The Excel file shows the same kind of formula as before, for example =(1200+1200*5%)/30/10.
Items (master list)
  • Machines, vehicles, people and recurring costs, each with category, reg no, unit, supplier, codes and rate.
  • A fuel item can be linked to its machine, so fuel on a day the machine did not work is flagged.
  • A dehire date removes the item from sheets after that date; the history stays.
Import an Excel sheet

Admin → Import → choose one day's file. The preview lists the items, rates, suppliers and any problems found (for example a rate divided by 31 days in a 30-day month). Nothing is saved until you confirm.

Supplier bills

Bills → month → each supplier shows the amount from the daily sheets. Record the bill number (and amount, to compare). The number is written into BILL NUMBER on that supplier's lines for the month, including final days; later days in the month get it automatically. “remove” undoes it.

Tally

Tally (accounts, admin) → pick a month → download 1. Ledgers and cost centres and 2. Vouchers. In TallyPrime use Import → Masters, then Import → Transactions. Only final days are exported. Month vouchers are one Purchase per supplier with the bill number as reference; day vouchers are one Journal per supplier per day. Each category maps to an expense ledger (editable on the Tally page) and SEC becomes the cost centre. A final day also has a “Tally XML” button.

Reports and month download

Reports → pick a month: total and change against last month, breakdowns by category, supplier, section and allotment, totals per day, and days with no sheet. “Download month” builds one Excel file for the month (final sheets only, or all).

Users and roles
RoleCan
SiteCreate, fill and submit sheets; add items
Accounts: 1st checkCheck and return sheets; change rates; supplier bills
Accounts: final approvalFinal approval and return; change rates; supplier bills
AdminEverything, plus users, settings, import, reopening final sheets

Users → Add a user → copy the one-time link and send it (WhatsApp, email). They choose their own password. A forgotten password: an admin makes a reset link on the user's page.

API and MCP for agents

Your name (top right) → API and MCP access → Create token. The token acts as you, with your role. It is shown once, together with ready-made settings:

  • MCP (Claude and other agents): server https://muster.ashds.dev/mcp with the header Authorization: Bearer <token>. Tools: whoami, list_projects, waiting_for_me, list_sheets, get_sheet, create_sheet, set_quantities, sheet_action (submit, check, approve, return, reopen), list_items, month_report, supplier_bills, record_bill.
  • REST API: GET https://muster.ashds.dev/api/v1 lists the endpoints (JSON).

Example request to an agent: “Read today’s sheet, set the excavator 148LD to 9 hours and submit it”, or “Which sheets are waiting for me, and what are their warnings?”

Your account

Click your name (top right): change your name or password, or sign out on every other device. Passwords need at least 10 characters.

Activity and history

Activity (accounts, admin) lists every change in the app. Each sheet also has its own History at the bottom.

Coming later

  • Notifications (email or phone) when a sheet waits for you; for now the dashboard shows it.
  • “Forgot password” by email; an admin makes a reset link instead.